-
CENTRES
Progammes & Centres
Location
Dabhol Revival: Good, Bad or Ugly?
Going by media reports and general perceptions, restarting Dabhol is a good thing. The state of
Not so much good from the past
India opened up the power sector in 1991 and invited offers for Independent Power Projects by Foreign Investors. The response was way above expectations. As a Business School case study on Dabhol put it, ‘internationally, India was in vogue for three reasons: the discovery of emerging markets by western financial institutions, economic reforms underway in the country, and a growing fear that China, the investor’s first choice, was spinning out of control.
The initial euphoria generated 189 offers from IPPs amounting to 75,000 MW involving an investment of Rs 2760 billion. Out of the 185 offers, Memoranda of Understandings (MoU) were signed for 95 projects that would yield 48,137 MW. There was international competitive bidding only for 32 projects. Eight fast track projects were identified and supported with sovereign guarantee of 16 per cent Return on Equity (RoE). Chief among these projects was the US$ 2.8 billion ‘Enron’ power plant in Dabhol with a capacity of 2184 MW. The Enron project was seen as a litmus test for the government’s commitment to the reform process and future progress in the world arena. In addition, this was also the first Build-Own-Operate (BOO) project, first to propose the use of Combined Cycle Generation Technology using LNG to be undertaken in the country. Dabhol was set up with Enron owning 65 per cent, GE and Bectel owning 10 per cent each and the Maharashtra State Electricity Board (MSEB) taking the remaining 15 per cent.
The Power Purchase Agreement (PPA) signed in 1993 by the ruling Congress government was shrouded in secrecy and was subsequently cancelled by the BJP government which defeated the Congress on the Enron issue. Eventually the BJP government renegotiated the PPA and signed on to terms that were in essence worse than those of the first PPA. Just when the project was approaching financial closure for Phase I in 1995, doubts began to surface on the rationale of the project.
Dabhol appeared to be unwarranted as the technology was unproven, fuel wrong for an Indian base load plant, and capital cost much higher than that of comparable plants. The entire project risk was borne by MSEB with most of the financial, political and legal provisions skewed against it. Mandatory recourse to international arbitration, take or pay clause, excessively high contract termination fee backed by sovereign guarantees from the state and central government rendered the cost of exit so high that MSEB was literally trapped.
In 1996 the second Phase of the project attained financial closure and construction resumed. In 1999 the Phase I plant began operations and MSEB started purchasing power from Dabhol at more than twice the rates (Rs 4.5/kWh or $ 0.95/kWh) it paid to other suppliers. Despite the revised PPA, MSEB’s financial status deteriorated fast once it started payments to Dabhol. MSEB defaulted on payment of about $ 22 million to Dabhol in 2000 and subsequently sought cancellation of the PPA alleging failure on the part of Dabhol to abide by technical commitments.
The dispute escalated and ended in closure of the plant along with the PPA being rescinded on the basis of mis-representation by Dabhol. Within a few months the Enron scandal broke out in the
Plenty of Bad
While there is much said about unscrupulous multinational corporations’ such as Enron exploiting the weaknesses of developing countries there were innumerous signals that strongly indicated that the Dabhol concept was unsuitable for
In 1993, before any contract was signed, Heinz Vergin, World Bank manager for
The Energy Review Committee headed by Madhav Godbole also found complete failure of governance of various governments at the state as well as the central government level in their dealings with DPC. In the report the committee found that the Enron power purchase agreement (PPA) had built in excessive payments to Enron from the Maharashtra State Electricity Board (MSEB) as a result of undue burden of the re-gasification facility, high recovery charges of shipping and harbour and O&M, and inflated claims of fuel consumption. The report was very critical of the lack of transparency in negotiations on the PPAs which had a direct impact on the final consumers.
More Ugly to Come?
Under the revival proposal for Dabhol which is being discussed by the Empowered Group of Ministers (EGoM), MSEB is to buy power from the project on a long-term basis at 80 per cent plant load factor for the entire 2184 megawatt capacity. The plant is expected to take around 18 months before it can be restarted. Prior to the restructuring exercise, the government is planning to settle GE and Bechtel's claims of around Rs 1500 crore (Rs 15 billion). The plan envisages a tariff of Rs 2.20 per kilowatt hour and allow Indian lenders to take over the company's assets under the Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act. The tariff comprises a capacity and variable charge of Re 1 each per unit and an LNG re-gassification charge of Rs 0.20 a unit.
During the restructuring exercise, Indian lenders are to first form a financial Special Purpose Vehicle (SPV) to buy out the offshore lenders and OPIC (Overseas Private Investment Corporation of the USA which was a major lender to the project) by issuing government-guaranteed bonds of over Rs 3000 crore ($ 700 million). A project SPV would then buy out the financial SPV in an all cash deal before redeeming the government-guaranteed bonds. Lenders may take over the secured debt and either lease, assign or sell the assets to the Project SPV.
According to the plan, 19 overseas lenders will get $230 million (at 20 per cent discount to their debt exposure); OPIC $225 million for general and political risk cover; export credit agencies $390 million, and GE and Bechtel $580 million which includes equity and cost of work done; $ 200 million towards restarting and completing the remaining work of Phase II; Indian debt of about $ 850 million. A crude estimate suggests that the total costs – only those that have been revealed so far – comes to about Rs 10,000 crore (~ $ 2.5 billion). Tax exemptions, import duty exemptions for equipment and LNG, loss of MSEB equity, loss of interest to Financial Institutions etc will add about Rs 1000 crore ( $ 1 billion) more to the cost.
The question that needs to be asked, especially by consumers and tax payers who will ultimately bear the cost, is whether revival of Dabhol at this cost will deliver proportional value? There are many issues behind that question. SPV equity of around Rs 1500 crore ($ 375 million) would mean a debt component of about 9500 crore or a debt-equity ratio of about 6:1 which is far above the norm of 3:1 for power projects. Another issue is the cost of delivered power. The demand profile has hardly changed in
As per the revival plan Dabhol will be a base load plant with 80 PLF. Using high cost fuel it is again not clear how Dabhol will compete with cheaper base load plants especially when open access comes into force. When buyers are free to choose expensive Dabhol power may become unviable.
There is also the question of the government settling the deal as per the revival plan and then offering the cleaned up plant to the private sector at unbelievably low prices. If one remembers Panna-Muktha & Raava oil fields which were sold off to the private sector without recovering even a small per centage of the cost incurred by ONGC in exploration and discovery of the fields this possibility does not seem to be so unlikely. The question of lack of transparency in negotiations is another serious issue. MSEB the sole customer for Dabhol power will undertake a financial obligation that eventually will pass on to the consumers and the consumers have every right to know how tariffs were arrived upon.
Politicians from ruling and opposition parties – both at the state and federal levels, past and present – were involved in Dabhol decision making right from Dabhol’s conception in 1991 – and they have an incentive in reviving the plant. For them this is a short term issue that matters only as long as they are in power. For consumers this is a long term issue and they better beware.
Team Energy ORF
(Views are personal)
The possibility of co-operation between
Sithara Fernando, JNU (Views are personal)
(K K Roy Chowdhury, Consultant Energy, ORF)
1.0 The Problem
The rapid rate of urbanization, a distinct feature in our economic development, would be accompanied with changes in composition of the growing population and types of economic activities. The rapid growth rate is expected to overwhelm the availability of the public resources. This has inherently generated a pressure on us to increase the power availability as well as its quality. Simultaneously, there is also a need to check the exodus from our villages in search of better opportunities to facilitate a sustainable development process. Reforms taking place all over
The generation capacity inclusive of non-utilities has risen from 2300 MW in 1950 to 1,33,000 MW as of today. Again, the generation has increased from 6 billion units to more than 630 billion units as of now. With so much of generation, there are still people who are left with no power. As a result, they live in darkness or resort to unfair means of hooking, theft (estimated around four hundred
Electricity Act 2003:
The act envisages and allows stand-alone systems for generation and distribution for rural and remote areas. Panchayats, user associations, co-operatives or franchises would also be permitted to manage distribution without requiring a licence in state government-notified areas. The central government is yet to bring out a policy on this.
India has shown significant growth in the power sector in terms of generation, transmission and distribution. As per statistics, nearly 80% of the villages have been electrified but how many of the villages receive a 24 hour supply is the question that needs to be answered. What is the value of such electrification when an average person doesn’t have access to power almost 6 to 12 hours a day? Power crisis and inaccess to electric power is also one of the factors of poor living conditions and hence poverty. Had this been taken into account to optimally design the village electrification programme to make it sustainable and raise the status of the poor and poorest who still account for the majority of the country’s population? Statistics again prove that nearly 1, 00,000 villages in
Reforms in
The Ministry of Power came out with an ambitious plan of adding 1, 00,000 MW during the 10th and 11th plans, during 2002 to 2012, to nearly double the installed capacity. Of this, the capacity addition for the 10th plan is about 45,000 MW. The Prime Minister launched the Hydro Power initiative in 2003 that envisaged a capacity addition of 50,000 MW during 2002 to 2012. As part of the rural electrification plan, the Government of India has set itself a goal of ‘Power to All by 2012’ under the Mission 2012, which implies electrification of all villages by 2007 and all households by 2012, to be supported by a massive central government subsidy. Three approaches are envisaged for this electrification: on-grid, off-grid, and hybrid systems. The central government has come up with a Rural Electrification Supply Technology Mission (REST), which was launched by the Prime Minister on
As a rising economy as we boast of, our plans and actions ought to have been driven towards complete eradication of poverty. That is not! We have actually failed to whole-heartedly address the various factors contributing to the poverty of the people, in doing so.
Electric power is one of them to enable people to come up. Otherwise, we contribute to deprive half the population of our country from having access to it. This does not help in achieving the country’s sustainable development either. We have to be also cautious in accepting the achievement figures declared by the government from time to time. For example, the village electrification figures may be misleading, because even those villages where even a single electric connection has been given is declared as electrified! This is ridiculous! This definition has now been changed and much more work is needed to electrify villages in the real sense to ensure that households also receive the benefit of electricity.
To ensure quality, reliability and continuity of electricity supply, investment would be necessary for adding new capacity and improvement in the supply system to eliminate wastage and misuse. It is however also necessary to create a mind set that the services provided have to be paid for at a reasonable price. Persons with low average income find it difficult to pay for the charges imposed on electrification and electricity consumption. This situation presents a special challenge to the government’s development agenda whose central objective is the improvement of the level of human welfare not only in urban areas but in all parts of the country.
Access to electricity, is a key element that cuts across all sectors in rural and urban living and development. Whether it is used to provide higher quality lighting for rural homes accustomed to kerosene lamps, power small vaccine refrigerators in clinics or pump water for irrigating small plots, the availability of even small amounts of electricity can make dramatic changes in the lives of people in remote rural areas. The key stumbling block in achieving this seems to be our political intervention in order to amass votes from the poor by delivering to them the message, “Electricity is a free of cost utility”; this blocks the mindset of the poor and hampers developmental work.
A Note on Electrification of Urban Poor:
Government of India’s policy for supplying electricity now to each household in the urban poor category under a franchisee scheme also stands to be myopic in nature since the following factors are not taken into consideration which has already been taken into account in many developing countries like Malaysia, Indonesia, even Bhutan to name a few:
Classification of household by gender, Size of the household, Source of income in the household, Frequency of cash flow, Type(s) of energy used by the household, Availability/proximity of the energy source, Modern energy possession(s), Energy initiative available, Expenditure on energy items, Expenditure on non–energy items. It has been estimated that the urban poor spend the maximum of their earnings on energy and in order to save money that they earn through hard work, they restore to unfair means like theft, etc. for getting supply of electricity. Moreover, it doesn’t take into consideration the facts that the patterns of energy use are influenced by income levels and types of economic activities. Again, among the relatively poor people, use of modern energy sources is not given priority. It is moreover pertinent to mention here that intended subsidies and preferential pricing doesn’t reach the poor and there stands a lack of payment flexibility for the urban poor leading to lack of faster development of the power infrastructure and thus increasing the energy poverty in a developing country like
2.0 The Possible Solutions
In off-grid areas, environmentally clean renewable energy technologies (RETs), such as solar photovoltaic (PV) and wind power, are becoming economically competitive with conventional, fossil-fuel based solutions. The potential applications include lighting for homes, schools and other public places; vaccine refrigeration for clinics; and water pumping for livestock, potable water supply and micro irrigation. These applications could be in stand-alone installations (such as solar home systems) or in minigrid configuration (such as a wind-diesel hybrid), depending on the density of user points. Renewable electricity from the sun, wind, water, ocean, geothermal and biological crop sources can be brought to nearly half the world’s population that today lives without power for just having no ground privileges the people of the civilized world enjoy, hence no sustainable earnings and therefore no voice to have an access to the miracles of science and technology to reform themselves even in this 21st century. As is evident from the monopoly structure of Power Industry in
Renewable energy systems are easily installed and maintained, and are available in varying sizes as per the requirement. They can supply power for households, villages, and regions at an one-time cost as low as Rs. 1000 per person. Reliable power sources, combined with access to credit, hold the key to economic growth and improved quality of life in rural, remote as well as unelectrified areas. Renewable energy offers a clean alternative to polluting fossil fuels, oil and coal. Rural areas of the developing world are prime markets for renewable energy technology and services. Key to success is building the capacity of local people and businesses to design systems and sell and service equipments. The Kyoto Protocol now in vogue extends its CDM(clean development mechanism) to help build this process which should be fully utilized by developing countries like
(Views are personal)
….To be continued
India’s Reforms in the Hydrocarbon Sector
What Has Been Accomplished?
What Remains to be Done? - X
……continued from issue 52
Upstream Sector Continued: The First Two NELP Rounds
The first bidding round (NELP I) was launched in 1999 with 48 blocks on offer. Deep water blocks were offered for the first time. 27 blocks on offer attracted 45 bids and Production Sharing Agreements (PSAs) were signed in April 2000 for 25 blocks of which 2 were onshore, 16 were shallow water offshore. Compared to the 10 years preceding NELP during which period only 23 agreements were signed this was a substantial improvement in process efficiency. Time taken for bidding and signing contracts came down from 3 years to about 7 months. An investment of $250 million was committed by the awardees in the first phase of exploration and expectations of striking large oil and gas reserves were high, especially in the Krishna–Godavari basin.
Under the Union Budget 1997-98, the Exploration & Production Sector was given infrastructure status enabling tax holidays for 5 years from the date of commencement of production and 30 per cent concession in Income Tax payable in 5 years. A separate petroleum tax code was to be put in place to facilitate investments. A tax holiday for seven years was provided after commencement of commercial production from blocks situated in the North Eastern Region of the country. In terms of price of crude & customs duty exemption level playing field was provided to the National Oil Companies and they were to be given international price of crude for production from areas obtained under NELP. Cess on crude oil produced from blocks under NELP was also abolished.
The second bidding round was launched in December 2000 in which 25 exploration blocks were offered. These included 8 deep-water blocks on the west coast, 8 shallow-water blocks both on the east and west coasts, and 9 on-land blocks. Blocks in
Expectations were high for NELP II as more than 215 companies and organizations had participated to view the data on blocks offered in ‘road-shows’ organised in London, Houston, Tokyo, and Singapore. However, global oil majors, including British Gas, Royal Dutch Shell, and Exxon-Mobil stayed away from bidding. Even companies such as BHP Petroleum, Pan Canadian, and Premier Oil which had bought data ultimately abstained from actual bidding. However some of the smaller independents, either by themselves or in partnership with domestic players, showed substantial interest. Hardy Oil bid jointly with Reliance for 15 of the 25 blocks. Cairn Energy bid for the
Of the four blocks which received the maximum bids, two were from the Cambay basin in
……to be continued
Pakistan says ‘no’ to Indian diesel, for now
June 22:
Even if
The Ministry of Foreign Affairs and security agencies had recently advised the government that a coordinated policy on import of petroleum products should be adopted keeping in view diplomatic, political and economic implications for overall progress of India-Pakistan relations.
NEWS BRIEF
NATIONAL
OIL & GAS
Upstream
Reliance closing in on 16th gas find
June 28, 2005. Reliance Industries is on the verge of a 16th gas discovery in deep sea block D6 off the Andhra coast, and has made a sixth consecutive gas find in block NEC-25, off Orissa coast. Reliance plans to begin producing 40 million standard cubic metres per day of gas from Dhirubhai-1 and Dhirubhai-3, two of the many discoveries made in the block, from 2008. The company is looking forward to continued drilling success on block D6. Reliance has completed drilling the sixth exploration well at NEC-25, resulting in the sixth consecutive gas find within the 1800 sq-km 3D seismic area.
Biggest gas find in
June 27, 2005. Gujarat State Petroleum Corporation Ltd (GSPCL) has made the country’s biggest gas discovery - 20 trillion cubic feet (tcf), worth US$50 billion - in the Krishna-Godavari (KG) basin in Andhra Pradesh. The find is a historical moment for the entire hydrocarbon sector in the country. The initial testing results indicate estimated reserves of 20 tcf of natural gas with a value of approximately Rs 2 trillion (US$50 billion). In 25 years, a 1,000 MW plant consumes one tcf of gas. The
ONGC gas find off A.P. coast
June 25, 2005. The Oil and Natural Gas Corporation has discovered gas in shallow waters off Andhra Pradesh coast. The gas was discovered in the ninth well drilled in GS-15 prospect, 15 km off Amalapuram coast. The present discovery was made south-west of the Ravva gas field. The well `indicated a significant hydrocarbon column' between an interval of 1,684 metres and 1,760 metres. This hydrocarbon column was 45 metres tall. While most of it is gas, the lower level indicates an oil leg. Oil found just below gas was called oil leg. An estimate of the quantity and quality of both oil and gas would be available in about a fortnight.
EU green signal for Iran-India pipeline
June 24, 2005. The European Union, which will soon kick-off an energy dialogue with India, has said it is not opposed to a US$4.16 billion pipeline project to pump gas from Iran to India through Pakistan. Energy dialogue is one of the key areas of India-European Union cooperation after the bilateral relationship was upgraded to “strategic partnership” level last year. The European Union, which has tremendous expertise on energy conservation, is scheduled to kick-off energy dialogue at the foreign secretary level now. The Indian delegation will be headed by foreign secretary Shyam Saran.
Kochi terminal estimate ups to US$460 mn
June 26, 2005. Petronet LNG Ltd (PLL) has revised upwards its estimate for the terminal in
IOC plans over US$ 413 mn investment in Haldia refinery
June 23, 2005. As part of the investment, the country’s largest oil refining and marketing company is preparing a detailed project report to reconfigure the refinery capacity from 6 mt now to 7.5 mt by ’09. The hike in refinery capacity is particularly aimed at making full use of improved supplies of crude at Haldia post-’06. The company’s Rs 1,200 crore (Rs 12 bn) Haldia-Paradip pipeline project is scheduled to be completed by ’06 and this is likely to lead to a much higher availability of crude at Haldia. IOC’s investment in Haldia comes as part of a larger plan to raise existing refining capacity from 41 mt to 66 mt over the next five years. IOC is also expanding capacity at its Panipat refinery to 15 mt and from 8 mt to 11 mt at
IOC to expand, upgrade regional sales network
June 23, 2005. Indian Oil Corporation Limited plans to 30 outlets to its network of 490 existing outlets in
IOC for stake in
June 22, 2005. Indian Oil Corporation is planning to take a stake in Singapore Petroleum Company (SPC) as part of its plans to become a diversified, transnational, integrated energy major. SPC, which has a market cap of about US$1.1 bn, has 50 per cent stake in Singapore Refinery Corporation's 273,000 barrels per day refinery and owns a 220,000 cubic meter capacity oil storage terminal in
US$4.36 bn for new GAIL projects
June 23, 2005. GAIL (
Iran regime change will not hit oil projects: Aiyar
June 27, 2005. Petroleum Minister Mani Shankar Aiyar said the change in regime in
CoPT hands over land to Petronet for LNG terminal
June 27, 2005. The Cochin Port Trust (CoPT) has handed over 32 hectares of land at Puthuvypu, off
No hike in gas price this year
June 23, 2005. The government has decided to cap the price of natural gas at US$3.86 per million British thermal unit for this year, providing relief to users who thought gas would become dearer. The Cabinet had last month decided that consumers, other than power and fertiliser companies, would have to pay market-determined prices for natural gas. The government has also issued instructions to Oil and Natural Gas Corporation (ONGC) and Gail India Ltd on the new pricing policy. Under the changed policy, ONGC will no longer have to subsidise natural gas bought from joint venture companies. Gail was making up for shortage of gas supplied under the government's administered price mechanism (APM) by buying the non-APM (joint venture) gas. This gas was being produced from fields given out to companies under the new exploration and licensing policy. Gail compensated for the higher price of non-APM gas by deducting the amount it paid to the ONGC. This practice had now been done away with.
Iran gas, Chhattisgarh coal to fuel Tata Steel plants
June 22, 2005. While Tata Steel plants in Iran will use the abundantly available gas in that country as an energy source to produce 3 mt per annum (mtpa), its 5 mtpa facility in Chhattisgarh will use the huge source of non-coking coal deposits in that state in making steel. With its abundant natural gas resources the conditions in
India's oil reserves to be reassessed
June 22, 2005. The directorate-general of hydrocarbons is planning to reassess
NTPC to start power hub in
June 28, 2005. State-run National Thermal Power Corporation (NTPC), plans to set up a 900 MW coal or LNG-based power plant in
NTPC
June 26, 2005. The National Thermal Power Corporation (NTPC) has got the much-needed coal linkage for its proposed 1,000 MW power project NTPC Tamil Nadu Energy Company Ltd. NTPC was earlier toying with the idea of importing feedstock through
Dabhol project to restart
June 23, 2005. The US$2.9-bn Dabhol power project is all set to be restarted with GE, one of the major equity holders in the project, assuring to begin work on restarting the project by month-end. The estimates by NTPC for the project restart are between Rs 600-800 crore (Rs 6-8 bn). GE along with Bhel will begin the assesment study for restarting the project by month-end or latest by the first week of July. The study will be carried at a cost of US$1-2 mn and will be completed in 45 days. While GE will do a detailed assement of the generator, steam turbine and gas turbine, Bhel will do the Bechtel part of the job which involves assement of all other equipment such as switchyard, cooling water tank, naphtha tank etc.
J&K plans for 10 power projects
June 23, 2005. In a bid to exploit the vast potential for power generation,
The Ahrabal Power Project designed to generate 15 megawatt power would cost about Rs 105 cr (Rs 1.05 bn). Nine similar power projects would be taken up at at various places in the state including Brenwar, Athwatoo, Mandi, Tangmarg and Hirpora during current year. In addition, about 25 mini and micro hydel projects with a cumulative capacity of 2000 MW would be started in
GVK bags 2 Uttaranchal power projects
June 23, 2005. Hyderabad-based GVK Industries Limited, an infrastructure major, has been awarded the 200 MW Mapang Bogudiar and the 170 MW Bogudiar Sirkari Bhyol Hydro Electric Projects by the Uttaranchal government. These two major projects are located on the Goriganga river in Pithoragarh district of Uttaranchal. GVK has bagged these projects amidst stiff competition through international competitive bidding route.
GVK will be executing the projects on a BOOT (build-own-operate-transfer) basis and expects to complete them before the scheduled time of 10 years through innovative methods of strategic alliances, project management expertise and competence in engineering and construction. Both Mapang Bogudiar and Bogudiar Sirkari Bhyol are challenging projects involving the construction of dams, tunnels, intakes, surge shafts, underground power houses, transmission lines, roads and other supporting infrastructure.
BHEL gets two AP power projects
June 22, 2005. Bharat Heavy Electricals Ltd will execute two 500 MW thermal projects at Bhoopalapally and
Transmission/ Distribution / Trade
Kerala to have
June 24, 2005. With a view to meeting the ever-growing demand for electricity in Kerala in the coming years, several long-term measures have been initiated by the State Government. A
Policy / Performance
Jharkhand set to get US$ 6.67 bn investment
June 28, 2005. Jharkhand state was close to finalising investment worth Rs 29,000 crore (Rs 290 bn) in the steel and power sectors, which included the L N Mittal-promoted Mittal Steel. The state government had also signed an agreement with the Essar group for enabling the later to construct a power project at the cost of around Rs 10,000 crore (Rs 100 bn) in Jharkhand. It expects an investment of Rs 10,000 crore (Rs 100 bn) for the second stage of the National Thermal Power Corporation project in the state and are hopeful that Rs 10,000 crore (Rs 100 bn) would be invested by the private sector.
Free power sought for washermen
June 27, 2005. M. Anjaiah, chairman of Andhra Pradesh Washermen Cooperative Federation Limited, has suggested to the Government to provide free power to `dhobighats' as is being supplied to farmers. He said that as an alternative, Government order on supply of power to `dhobighats' at Rs. 250 a year (up to 5 hp) and Rs.400 (up to ten hp) should be implemented.
No increase in power tariff for now
June 27, 2005. With North Delhi Power Limited (NDPL) demanding stability or reduction in power tariff in view of "over-achievement" of its revenue targets, the Delhi Government is faced with a tough choice of deciding between going in for a power hike or opting for subsidy to small consumers and making the bigger consumer pay more. Although the Delhi Electricity Regulatory Commission (DERC) is ready with the tariff order, it is learnt that the Delhi Government has asked it to hold it back. It may be noted that the Delhi Government has all along maintained that DERC is an independent body and it has no control over its functioning. But it has managed to get the order on tariff held back for quite a few days now. Experts are of the view that if the Delhi Government is serious about the whole affair then it has the power to issue policy directions to DERC on an important matter, something that could help in putting the tariff order on the backburner. Reflecting a spirited performance, NDPL has come out openly against any power hike on the assurance that the present procurement rates should be allowed to stabilise. With the NDPL setting the tone for not disturbing the present tariff structure or seeking reduction, the job of the Delhi Government has been made all the more difficult due to the increasing pressure from consumers and the poor situation on the power front. Despite the performance of BSES Yamuna and BSES Rajdhani coming in for flak from various quarters, the Delhi Government has failed to act or file a formal complaint against it with the DERC.
Coal supply to hinge on use
June 27, 2005. The government is planning to tighten coal supply by asking coal users to furnish a letter of comfort certified by financial institutions while seeking a linkage. The government is insisting on a letter of comfort after finding that many companies are not using their linkages. The reasons for linkages lying idle ranges from a plant becoming sick or being unable to add more capacity to companies opting for better variety of imported coal. According to Ministry of Coal, companies will be asked to declare a time schedule by which they expect to achieve project milestones, failing which their linkages could be cancelled. The demand for coal linkages was not very high till two years back. The spurt in demand was owing to an increase in global coal consumption and companies relying more on domestic coal. The increase in thermal power generation also added to an increase in the demand for coal. The plant load factor (PLF) of power houses has gone up from 69 per cent in 2000-01 to 75.2 per cent in 2004-05. The increase in PLF has adversely affected coal supply to the non-core sector. This sector has about 2,800 linked consumers even after Coal
Coal prices to be regulated
June 27, 2005. The Government of India has agreed to put in place a mechanism to regulate coal pricing which has a huge bearing on the cost of generation of power. The Centre has decided to refer the coal pricing issue to the Tariff Commission at the national level which would harmonise the interests of consumers and producers and arrive at a proper pricing structure. This step is taken in the light of the Coal India Limited’s decision to increase coal prices by around 15 per cent with effect from June 2004.
US$79 for rural electrification in Kerala
June 26, 2005. The Kerala State Government had earmarked Rs. 343 crores (Rs 3.43 bn) for the Centre-sponsored Rajiv Gandhi Rural Electrification Scheme for providing power connection to 100,000 villages. The amount would be utilised for electrification of 2,573 villages in the State. A Rs.7.74-crore (Rs 77.4 mn) scheme would be implemented to end the low voltage problem in Taliparamba and nearby areas. Similar schemes would also be launched in Koothupramba and Mattannur. As many as 548,000 new connections had been provided in 2005 including 122,000 connections for families in the below poverty line category.
Power outages lowest in Kolkata
June 24, 2005. The Central Electricity Authority's (CEA) evaluation for March 2005 identified Kolkata as the city with the lowest number of trippings per feeder and
AP to seek additional gas supply for IPPs
June 24, 2005. The Andhra Pradesh plans to seek the Centre's support for additional gas allocation for power projects. State would request the Prime Minister to initiate steps to ensure availability of natural gas as per agreements made with GAIL for all the four sanctioned independent power producers (IPPs) in the State. GVK, Konaseema, Vemagiri and Gauthami, with a total installed capacity of 1500 MW, need natural gas supply. Any failure to ensure gas supplies to these projects would mean an additional burden of Rs 1,000 crore (Rs 10 bn) per annum towards fixed charges, without a single unit of power being generated and supplied. As per the terms and conditions agreed to with these gas stations, the Government will have to shell out money even if they were idle.
NTPC asked to import 400,000 t of coal
June 24, 2005. In order to tide over the existing fuel and gas shortages for power projects and meet its targets of 41,000 MW for the Tenth Plan, the ministry of power has asked the National Thermal Power Corporation (NTPC) to import 3.5-4 lakh tonnes of coal during the current fiscal through MMTC India limited. Gas shortages of around 20 mmscmd for the existing projects is also being tied up in co-ordination with the petroleum ministry. While 10,959 MW has already been implemented, 24,152 MW capacity is under execution and another 1,815 MW is under award. About 5,000 MW capacity requirement will be met from captive generation. This will ensure that targets for 10th plan are met.
Himachal tie-up with
June 24, 2005. Himachal Pradesh would explore the possibility of collaboration with
India to build Afgan power project
June 24, 2005. In a major move to help war ravaged Afghanistan rebuild its infrastructure, India agreed to construct a 220 KV double circuit transmission line to start power supply from Uzbekistan to Kabul and a power sub-station in the Afghan capital at a total cost of Rs 478.72 crore (Rs 4.79 bn). The approval to the two projects was granted by the Union Cabinet. The transmission line from Pul-e-Khumri to
KCCI calls for power import from
June 23, 2005. Kanara Chamber of Commerce and Industry (KCCI) has said that
Coal linkages to 22 captive plants
June 23, 2005. The ministry of coal and mines approved long-term coal linkages of 4636 mt to 22 captive power plants. The Korba super thermal power station expansion stage II of NTPC has been sanctioned 2.233 mt of coal and the Mauda thermal power station, also under NTPC, has been given 5 mt per annum. The 22 captive power plants with a total capacity of 1,128.75 MW would benefit from the approvals granted. While the Korba unit of NTPC would get coal from the South Eastern Coalfields, the consent of the Railways to move coal from IB Valley of Mahanadi Coalfields has bailed out the Maunda unit with a 1,000 MW capacity. The other power plants granted linkages include Balco (540 MW), Hindalco (40 MW), Aarti Steels (80 MW), Shriram Fertilizers and Chemicals (40 MW) and Lafarge
UP power tariffs to go up next month
June 23, 2005. Power tariffs are set to be hiked for the fifth time in a short span. A new tariff structure is likely to be announced by the UP State Electricity Regulatory Commission next month. The UP Power Corporation (UPPCL) in its Annual Revenue Requirement (ARR) for 2005-06, submitted to the commission in March, asked for a hike of 12–18 per cent for various categories of consumers. The UPPCL expects to mobilise Rs 600 crore (Rs 6 bn) more in 2005-06 through revisions of power tariffs. Power tariffs in UP are lower than in several neighbouring states and there is ample scope of further hike. The corporation is of the view the average cost of supply of power is Rs 4.05 per unit while the average selling cost is only Rs 2.81 per unit. Moreover, the cost of power procurement is likely to go up by 16.87 per cent in two years, while the average hike in power tariffs is just 3 per cent. Even after five years of reform in the power sector, the financial position of the UPPCL remains grim. In 2004-05 cash losses of the UPPCL were Rs 2,761 crore (Rs 27.61 bn), that too after it received a subsidy of Rs 1,002 crore (Rs 10.02 bn) from the state government. The UPPCL maintains there was a subsidy shortfall of Rs 500 crore (Rs 5 bn) because the power regulator had asked the state government to pay a subsidy tune of Rs 1,500 crore (Rs 15 bn).
NTPC to pay higher to GAIL than Reliance for LNG
June 23, 2005. National Thermal Power Corporation (NTPC) has agreed to pay US$4.1 per million metric british thermal unit (mmbtu) to GAIL (
World Bank to fund AP projects
June 22, 2005. Diluting the free power policy has, at last, paid off. The World Bank has agreed to fund various projects in Andhra Pradesh. It had initiated discussions with the state government on free power and the recent steps taken by the government. Billing rich farmers and metering agriculture power are very positive steps, World Bank said. The Bank is keen to support the state government and work together in various development and poverty reduction projects. It is in process of clearing the US$230 mn urban infrastructure project proposed by the government.
Short circuit: Sayeed, PM differ on free power
June 22, 2005. Power minister PM Sayeed and Prime Minister Manmohan Singh don’t seem to be speaking the same language when it comes to power sector reforms, especially on the issue of providing free power. The power minister, P. M. Sayeed says that the Centre would not interfere with a state’s decision to provide free power. Mr Sayeed put the ball in state governments’ court, by saying that it was up to political parties in the states to decide whether or not to provide free electricity to certain sections of society. Sayeed rationale for putting the ball in the states’ court is simple. Electricity is a matter on the concurrent list and states had the freedom to make their own choices. He said that the Electricity Act, 2003 also provides (freedom to) state governments to give relief to any section of the society, provided they compensate for it.
SPV for Dabhol in next 10 days
June 22, 2005. A special purpose vehicle (SPV) for the restart of 740-MW phase I of Dabhol project would be set up in the next 10 days. Comprising National Thermal Power Corporation (NTPC), GAIL India and financial institutions (FIs), the SPV would be the joint owner of the project with an equity participation of Rs 1,500 crore (Rs 15 bn). This is an interim arrangement to ensure restructuring and completion of the phase-II (1,444 MW) which is almost 93 per cent complete. The Centre has already decided to provide guarantee of close to Rs 3,150 crore (Rs 31.50 bn) to the SPV. After completion and stabilisation of the project, it would be sold to a private operator. The lenders would move the Debt Recovery Tribunal for the transfer of Dabhol assets, free of encumbrances and charges. Financial institutions would exercise their enforcement rights as secured lenders to DPC to the project SPV. NTPC and GAIL would operate and manage the facility.
Plan panel revises down investment
June 22, 2005. Resource constraints has forced the planning commission to scale down investments by 12.5 per cent in crucial areas including agriculture, power and manufacturing. The sectors identified by national common minimum programme (CMP) as thrust areas for boosting economic growth and investments will now get only Rs 3,582.2 crore (Rs 35.82 bn) in the remaining two years of the tenth plan as against the original allocation of Rs 4,081.5 crore (Rs 40.82 bn). The mid-term appraisal (MTA) of the tenth plan has reduced the public investments by 19 per cent especially in agriculture, manufacturing, electricity, and public administration etc. It said that investments in manufacturing and power sectors were low, mainly due to the inability of PSUs concerned to generate requisite amount from internal resources, while in other areas it was the lack of sufficient budgetary resources. Investments in electricity, gas and water supply has almost been halved to Rs 174.5 crore (Rs 1.75 bn) from the tenth plan level of Rs 251.6 crore (Rs 2.52 bn).
CERS opposes higher power tariffs for schools
June 22, 2005. Ahmedabad-based Consumer Education and Research Society (CERS) has strongly opposed the state government's decision to charge commercial rates for electricity supplied to schools and other educational institutions. In June 2004, the Gujarat Electricity Regulatory Commission (GERC) had created a special tariff, LDF-III, for educational institutions registered with the charity commissioner. The LDF-III tariff provides for fixed charges of Rs 26.25 per month and energy charges of Rs 3 per unit. Schools and educational institutions were earlier charged tariffs at par with residential areas and this change has been made for a year or so now.
Programme to improve power transmission in Kerala
June 22, 2005. Power transmission in Paravur township in Kerala is set to improve with the launching of the Accelerated Power Development and Reforms Programme at Paravur. The programme involves revamping the whole distribution system with the addition of extensive network. Thirty-three new distribution transformers and 175 capacitors will be installed to improve voltage and stability. All the existing distribution transformers at Paravur section will be renovated.
INTERNATIONAL
New gas field in
June 28, 2005. A new gas field, capable of pumping 40 million cubic feet of gas per day, has been discovered in an area about 95 km west of the eastern oil city of
Aramco offers 4 petroleum projects
June 28, 2005. Aramco offered contractors during a meeting at the Eastern Chamber of Commerce four potentially giant projects to support its oil production in the Kharasaniya, Shaiba, Khorais and Hawiya fields. The projects are expected to be initiated in 2006 and 2008. They are divided into three groups: Giant projects with a cost of around $2 billion; medium projects between $3 million and $200 million and small projects for less than $3 million. Aramco also announced that it has completed the architectural design of a group of giant and medium projects and will send out invitations for bidding on them later.
Shell paves the way for future as natural gas giant
June 23, 2005. Shell will transform itself into a global gas major over the next ten years, producing more natural gas than crude oil, as the company steps up investment in ten multibillion-dollar projects, known as “elephants”. Shell expects that its production of hydrocarbons will rise from current levels of 3.5 million barrels per day (bpd) to 5 million bpd as the company raises its investment in research and new technology. The business would change, with unconventional oil, such as tar sands, heavy oil and gas-to-liquids technology, playing an important part in the growth. The growth would come from Shell’s vast oil sands deposits in
Petrobras increases target to 600,000 b/d
June 23, 2005.Brazil's state oil company, Petrobras, increased its international crude production target for 2010 by some 100,000 barrels per day to 600,000 bpd. The increase in production will largely come from the
Oil to continue above $49: OPEC
June 22, 2005. OPEC, the producer of about 40% of the world’s oil, expects crude oil to trade above $49 barrel in
Accel energy group JV with
June 27, 2005. Accel Energy Group announced a joint venture with one of the largest refineries in central
Sempra has plans to expand liquefied natural gas terminal in Baja
June 25, 2005. Although construction of Sempra Energy's liquefied natural gas terminal in
Transcorp, Zenon sign mop to build refinery in
June 22, 2005. Transnational Corporation of Nigeria Plc, a newly mega company signed a MoU with Zenon Petroleum and Gas Limited to build a refinery in
SSGC inks new gas sale agreement
June 25, 2005. A 30mmcfd supply of gas will be available to Sui Southern Gas Company following signing of a new "Term Sheet of Bhit Gas Sales Agreement (GSA)" at SSGC. The agreement was signed between SSGC and ENI Pakistan - the operators of Bhit and Badhra gas fields in Dadu district, on behalf of their joint venture partners
Enterprise invests in natural gas plants
June 23, 2005. Enterprise Products Partners L.P. would pay $144 million to acquire seven natural gas liquids, or NGL, facilities from propane retailer Ferrellgas Partners LP, and pay $25 million to buy stakes in two pipelines from energy provider Williams Cos. to bolster its domestic NGL portfolio.
Chevron Caspian pipe could pump 1.55 mln bpd by '09
June 22, 2005. A Chevron-led pipeline from
TNK-BP set to enter gas markets
June 22, 2005. TNK-BP is set to become one of the largest and most active participants of the gas market, supplies, trading and gas and gas condensate transportation, has stated at the 3rd Russian Oil and Gas Congress. TNK-BP has chosen to cooperate with Gazprom, and has already held rather many meetings. At present, the company does not possess any proven gas reserves, yet it annually produces some 4.5bn cubic meters of associated gas. It has worked out short- and long-term development variants for its gas business. In the long-term, the company proposes to develop the giant Kovykta field in
UK's BG signs LNG purchase pact with
June 21, 2005. British oil and gas group BG Group had entered into an agreement with
Liberia signs offshore exploration deals
June 21, 2005.
Kuwait oil co. to seek pre-qualify bids on refinery
June 26, 2005. State-run refiner Kuwait National Petroleum Co. will invite international companies to pre-qualify to bid to build a new refinery with a capacity of up to 630,000 barrels per day. A committee has already been formed to evaluate the pre-qualification applications by potential international bidders. The new refinery project is expected to be completed in 2010, the same year the aging 200,000-bpd Shuaiba refinery will be shut down. KNPC has appointed Fluor International, part of U.S.-based construction and engineering contractor Fluor Corp., as adviser for the bidding process. KNPC runs three refineries with a combined maximum processing capacity of 930,000 bpd. The new environmentally-friendly refinery will produce low-sulphur fuel oil for the country's water and electricity generating plants.
Russia to increase energy production and export
June 25, 2005.
China to fill petroleum reserve this year
June 24, 2005.
Gazprom plans major expansion into oil
June 24, 2005. Russian gas giant Gazprom is planning a major move into oil and wants to emulate BP, Exxon and Shell by getting half its income from oil, Gazprom is the world's biggest gas company, but many of its gas fields also have oil and in the first five months of this year it produced an average of 260,000 barrels per day of oil and gas condensate, almost all of which it sold within Russia. They are studying the possibility of new acquisitions in this sector in
Iran duty-bound to address global crude demands
June 23, 2005. As a committed OPEC member and an oil producer,
Conditions for India-Myanmar pipeline
June 23, 2005.
Oil giant faces suit over flaring gas
June 22, 2005. Shell and its partners found themselves facing a legal suit from local rural communities and western environmentalists over allegations of causing pollution and global warming by flaring gas in
Shell readies proposal to join Gazprom’s $10 bn Arctic project
June 22, 2005. Royal Dutch/Shell Group,
Chevron’s approval of major refining project
June 21, 2005. Chevron Global Refining plans to increase the capacity of the Pascagoula Refinery's Fluid Catalytic Cracking Unit (FCCU) by about 25 percent, from a current capacity of 63,000 barrels per day. This project will increase the Pascagoula Refinery's gasoline production by 500,000 gallons per day. With environmental permits in place, construction of the $150 million FCC Project is expected to begin next month and is expected to be complete in late 2006.
Newfield signs production agreement for oil fields
June 21, 2005. Newfield Exploration Co. is set to develop the
Naturkraft builds
June 24, 2005. The board of
Skanska & partners to build a power plant in
June 22, 2005.
Taiwan to switch from nuclear fuel to coal
June 28, 2005.
Japan is giving up on nuclear reactor bid
June 22, 2005.
EU wants 20 pct cut in energy use by 2020
Jun 22, 2005.
Russia to launch energy dialogue with India,
June 22, 2005.
Renewable Energy Trends
National
REL forays into renewables
June 24, 2005. Reliance Energy (REL) has tied up with General Electric of the
Global
IEA sees big prospects for biofuels
June 24, 2005. With oil prices at over $50 a barrel, biofuels have received renewed attention and have led to a surge in new bio-energy activity in industrialised and developing countries. A huge amount of investment is flowing into both production and development of biofuels technologies. The agency has shown interest in supporting cost-effective outcomes. In many southern countries, biofuel may be used for cooking and `agricultural needs. However, use of biofuels, such as ethanol and biodiesel, in the transport sector of all countries can help reduce dependence on petroleum. Many other factors are also seen driving greater biofuel production and use, including agriculture and trade reform, improving energy access to the rural poor, local and global environment challenges and new, more efficient conversion technologies. Flexible fuel vehicles that are now entering the market in Brazil, the US and other regions permit the use of any mixture of ethanol and gasoline, empowering consumers with competitive options and reducing both the demand for oil and the economic and security risks associated with it.
Wind farm project in the
June 24, 2005. A
ORF ENERGY NEWS MONITOR Subscription Form Please fill in BLOCK LETTERS |
|
Subscription Terms |
Subscription Rates for Corporates: Rs. 15,000/- per annum. This includes one hard copy as well as soft copies to staff of the subscriber. Selected ORF publications as well as advertising space in one issue of the ORF Energy News Monitor are offered as introductory free gifts. Substantial discounts available for NGOs, Research Institutes, Libraries, Educational Institutes, Industry Associations & Chambers, Individuals & Students. |
Yes! I/we would like to receive copies of the weekly ORF Energy News Monitor for a period of ______year(s). I/we shall be entitled to one hard copy along with the option of soft copies to a list of e-mail addresses provided by me/us for the period of subscription. I/we also note that I/we shall get select ORF publications brought out during the period of subscription free. Name………………………………………………………Address…………….………………………………………………………………………………………… Telephone……………………Fax………………….E-mail…………………. Please find enclosed cheque/Bank Draft No............................dated …………………drawn at Please fill in this form and mail it with your remittance to ORF Centre for Resources Management OBSERVER RESEARCH FOUNDATION 20 Rouse Avenue New Delhi - 110 002 Phone +91.11.3022 0020 extn 2120 (Janardan Mistry) Fax: +91.11.3022 0003 E-mail: [email protected] |
Registered with the Registrar of News Paper for
Published on behalf of Observer Research Foundation,
Disclaimer: Information in this newsletter is for educational purposes only and has been compiled, adapted and edited from reliable sources. ORF does not accept any liability for errors therein. News material belongs to respective owners and is provided here for wider dissemination only. Sources will be provided on request.
Annual subscription: Rs 15,000/$ 750
[1] Xia Yishan (China Institute of International Studies), ‘Trilateral cooperation in the energy resources sector between
[2] Ibid., p. 74.
[3] Chietig Bajpaee, ‘
[4] ORF News Monitor, Vol. 1 issue 34, p. 10, and Vol. 1 issue 36, pp. 11-12.
[5] Bajpaee, op cit., p. 2.
The views expressed above belong to the author(s). ORF research and analyses now available on Telegram! Click here to access our curated content — blogs, longforms and interviews.